Subcontractor Login

« Historical

Historic Restoration of Metro Courthouse

Hardaway Construction - Historic Restoration of Metro Courthouse
Hardaway Construction - Project ImageHardaway Construction - Project ImageHardaway Construction - Project ImageHardaway Construction - Project ImageHardaway Construction - Project ImageHardaway Construction - Project Image
Hardaway Construction - Project ImageHardaway Construction - Project Image
Location: Nashville, TN
Owner: Metropolitan Government of Nashville and Davidson County
Architect: Barge Waggoner Sumner & Cannon, Inc.

The Metropolitan Historic Courthouse project was a challenging renovation and restoration of the 1937 art-deco style courthouse. The 270,400-SF, 11-story courthouse was not only a Historic restoration, but the completed project had to meet modern day codes and included replacement of all mechanical and electrical systems, security enhancements including new secure elevators and stairways, life safety, office and administrative spaces, finishes, and the lobby areas, courtrooms and the central stairway were restored.

This project required a tremendous amount of experience, creativity, an energetic workforce, and an optimistic project team in which cooperation would be a necessity. A challenge for the mechanical and electrical engineers was routing ventilation ductwork and controls throughout a building that was not originally centrally cooled. In most cases, this was accomplished without lowering the ceilings in spite of the low floor-to-floor heights. 

In order to preserve the Historic spaces, the finishes were carefully removed or protected until they could be properly and meticulously replaced or restored in the building. These materials included courtroom custom wood paneling, terrazzo flooring, marble walls and steps, custom metal railings and Historic lighting. The entire exterior façade, including stone, marble, stone pediments, and steel awning windows went through an extensive restoration process. The re-construction of the exterior public terrace contained two granite fountains, stone pavers, plinths and steps, which were also a part of the renovation / restoration process. 

All required work had to be accomplished while the structure was being altered to accommodate two new elevators and stair shafts, requiring slab and beam removal and replacement for 11 stories from the basement to new penthouses on the roof. Innovative means and methods had to be incorporated throughout the construction process in order to maintain a dry building as the existing roof was removed and the entire building re-roofed.

« Back to Historical

Follow us on:
Hardaway Construction on Twitter Hardaway Construction on LinkedIn