Quebecor World Printing Plant - Press Bay 331 Phases I & II

Hardaway Construction - Quebecor World Printing Plant - Press Bay 331 Phases I & II
Location: Augusta, GA
Owner: Quebecor World Printing
Architect: Centric Architecture

This 12,960 SF Design-Build project was delivered in two phases.   Phase I included the addition of a switchgear room and offices, and also included electrical and mechanical improvements for stitching equipment.  This phase was completed in 6 months.  

Phase II included preparation of a press bay to receive a new rotogravure printing press manufactured by the Italian Pressmaker Cerutti.  Also, included were new foundations and renovations to the HVAC and electrical systems.  This phase was completed in 8 months.